Schedules and Timelines

For sites the web team is required to build:

Simple projects
(6 pages or less; no-back-end programming)

5 weeks from the time the navigational layout (wireframe) is completed by the client and site content is submitted
Complex projects
(7 pages or more and/or back-end programming required)
10 weeks from the time the navigational layout (wireframe) is completed by the client and site content is submitted


For all other sites the web team builds: 10 weeks from the time the navigational layout (wireframe) is completed by the client and site content is submitted

Project schedules begin when the web team receives a completed wireframe and the final, approved content for a site.

If you have not finished your planning or creating your content by the minimum time requirement noted above, and/or do not provide any additional required content and/or feedback according to the project schedule we prepare for you, your project will experience delays.