ECC-HVAC Replacement Project Update (July 2008) Two of the three units have been repaced and are up and running. The third unit is being worked on now and will be working soon. Phase One - Air Handler Units Musser Mechanical is in the process of replacing three large air handling units that are original to the building (1972). These units move the air in the campus center. The first unit was completed on April 4th. Estimated completion date for this project is the middle of June.
Phase Two - Cooling Tower The origianl cooling tower to teh building will be replaced. This work will be conducted during the fall and winter heating season.
|