Click here to return to Messiah College's homepage
Click here to return to the Department of Facility Services homepage
Quicklinks

 
Construction Projects Home
   
Current Projects:
Bullet North Complex Underground
Hot Water Storage Tank
President's Residence
ECC-HVACC Replacement
Frey Hall Solar Project
Treona Parking Lot
Kline Fume Hood Replacement
Chapel Fire Alarm System
Oakes Museum Dehumidification
   
Completed Projects:
Anderson Field Resurfacing
Fine Arts Miller Auditorium Stage Lighting
Naugle Dehumidification
Bullet Mellinger Apartment Projects
bullet Musser Farm House Demolition
Sports Center Fire Alarm System
Pool Renovations
Boyer Hall Emergency Generator
Fry Apartment Renovations
Barlett/Hamner Demolition
Kline Hall
Harrisburg Institute
Anderson Field
   
Contractor and Consultant Database Sign-up
Plan Room
Resource Room

Related Links:
   

Fine Arts - Miller Auditorium Stage Lighting

 

August 2008 -

The stage lighting is finished.

 

July 2008 -

Currently we are waiting for the vendor to complete the start up of the equipment.

 

June 2008 -

The stage in Miller auditorium will be receiving new lighting.  This project will consist of new wiring and equipment to be used for theater productions.  The project will start in the beginning of May and is scheduled to be completed by June 20th.  Fullerton Electric is installing the new wiring and Bandit Lighting is providing the new equipment.


 