Click here to return to Messiah College's homepage
Click here to return to the Department of Facility Services homepage
Quicklinks

 
Construction Projects Home
   
Current Projects:
Bullet North Complex Underground
Hot Water Storage Tank
Bullet Mellinger Apartment Projects
President's Residence
ECC-HVACC Replacement
Naugle Dehumidification
Frey Hall Solar Project
Fine Arts Miller Auditorium Stage Lighting
Treona Parking Lot
Kline Fume Hood Replacement
Anderson Field Resurfacing
Chapel Fire Alarm System
Oakes Museum Dehumidification
   
Completed Projects:
bullet Musser Farm House Demolition
Sports Center Fire Alarm System
Pool Renovations
Boyer Hall Emergency Generator
Fry Apartment Renovations
Barlett/Hamner Demolition
Kline Hall
Harrisburg Institute
Anderson Field
   
Contractor and Consultant Database Sign-up
Plan Room
Resource Room

Related Links:
   

Pool Renovations

Monday, January 28, 2008

The pool flooring is finished and ready for all to enjoy!

                               The flooring is completed.

Tuesday, January 22, 2008

The last coat of color has been laid.  The final step will be to cover that with several coats of epoxy.

     The last coat of color is done.     The last coat of color is finished.     The last coat of color is completed.

Friday, January 18, 2008

The sub-flooring is just about ready for the flooring to go down.

     Sub-flooring      Final Stages     Work supplies

Friday, January 11, 2008

Work continues on the flooring.  Preparations are being done to lay the new deck.  Epoxy is put down and then covered with fiberglass material. 

     The deck is being prepared for the new flooring.    Another view of the floor as it is ready.Different stages of the flooring preparations.

Thursday, January 3, 2008

As work continues, the pools are being filled, the drains are being worked on and the decking is sanded for new flooring.

    the pools are being filled     the drains are worked on.     the flooring is sanded.

Wednesday, January 2, 2008

The sub-flooring is being placed in preparation for new decking to be laid.

     sub-flooring around pool edge     working on laying the sub-flooring     The pool is kept wet while emptied.

Tuesday, December 18, 2007

The pools and deck are being sanded.

    Decking is being sanded.      The diving pool is sanded

Monday, December 17, 2007

The pools are emptied to do repair work in them.

    The main pool is drained and being cleaned.     Diving pool is draining 

 