Frey Hall Storage Shed

 

Frey Hall Storage Shed Exterior 1.28.2010

 

Frey Hall Storage Shed  Interior 1.28.2010  

 

Frey Hall Storage Shed Interior Garage Doors 1.28.2010

December 2009 -

The electrical installation is complete.  We are waiting for the final township inspection at which time engineering can move into the new storage

facility.

 

November 2009 -

Electrical work moving along on this project.  Contractor will be back to insulate the building.  Concrete pad being poured from shed to Frey Hall.

 

Frey Hall Storage Shed Concrete Pad  

 

Frey Hall Storage Shed Concrete Pad

 

Frey Hall Storage Shed 11.20.2009 

 

Frey Hall Storage Shed   11.20.2009

 

October 2009 -

Outside/inside skin and doors have been installed.  Electrical grading and concrete to be completed in next two weeks.

 

Frey Hall Storage Shed Inside View 9.18.2009 

 

Frey Hall Storage Shed Fullerton Electrical work 9.18.2009

 

Frey Hall Storage Shed Exterior View 10.20.2009 

 

Frey Hall Storage Shed Exterior View 2 10.20.2009

 

September 2009 -

The engineering department has required more storage due to the addition of new programs.  An area behind Frey Hall has been designated for a new storage building.  The building will be 33 ft. wide by 30 ft. deep and will have pole building construction.  This building will allow storage of equipment that is taken up much needed space.

 

Frey Hall Storage Shed 9.15.2009

 

Frey Hall Storage Shed  9.15.2009

     

Frey Hall Storage Shed 9.17.2009