Slate Roof Projects

 

signage of vendor

July 21, 2010

This project is completed.  The slate roofing on 12 different buildings have been repaired or replaced.

June 2010 -

Updated shortly.

 

Hostetter Chapel roofing project 6.11.2010  

 

Hostetter Chapel roofing project 6.11.2010

 

roofing project 6.11.2010                                 

 

Hostetter Chapel roofing

 

May 2010 -

This project is winding down.  The contractor is finishing work at Mellinger building.  They will be moving to Hostetter Chapel to replace roof slates and copper valleys.  The last building they will be working on is Murray Library.

 

Leeland Roofing ongoing project   

 

Leeland roofing project ongoing

March/April 2010 -

This is an on going deferred maintenance project.  The contractor is replacing broken slate and installing snow guard.  The snow guard will help prevent damage slate in the future.  The snow guards will also help prevent snow from sliding off the roof.

 

February 2010 -

The contractor has been on campus mid January and continues to replace missing and broken slate.  They will also be installing snowguard on all applicable roofs.  Due to recent heavy snowstorms, their work has slowed down but will include damage from the storms.

 

Naugle roof repairs from the snow 2.24.2010  Naugle roof repairs  Naugle roof repairs 

 

Naugle roof repairs  Naugle roof repairs 2.24.2010

January 2010 -

Over the next several months, the contractor will be replacing missing and broken slate on all campus buildings.  Please be aware of work being done overhead and stay clear of areas taped off or coned off.

 

Slate Roof at Climenhaga Homestead 1.29.2010       On the roof at Climenhaga Homestead  1.29.2010