Fry Apartment renovations


Fry apartments is undergoing major renovations from June 2006 to August 2007.

The project includes:

  • Replacement of the heating and air conditioning systems
  • Installation of a central hot water system
  • New windows
  • Redesign of the kitchen
  • New appliances
  • New flooring
  • Painting
  • New furniture

Questions should be directed to Russ Ehrich, Project Manager

Update (August 16, 2007)
Fry apartment project is complete and housing will be open as scheduled for the fall.

     Fry Apartments Living Room     Fry Apartment Bedroom    

    

     Fry Apartment Kitchen     Fry Apartment Kitchen (another angle)

Update (August 10, 2007)
Renovations are moving along on schedule. Sections A & D have been completed, furniture is moved in and the contractor is working on a punch list. C-section is in final cleaning. Furniture is going back in B-section. All inspections to this point have been favorable and have not slowed up the project. Landscaping has been scheduled and will start soon.

Updated Photos (July 30, 2007)

Finished Kitchen in Fry D      Bedroom in Fry D Apartment     Another Kitchen Photo in Fry D Apartment

 

Update (July 1, 2007)
This renovation project is proceeding on schedule. All of the mechanical work in D-section is completed. Tile and carpeting is being installed this week. The contractor is continuing through the building in sections. The general contractor estimates that they are 65% completed with the project. (See pictures below)

   Fry D202 Bathroom     Fry D202 Tub     Fry D202 Bathroom Closet        

   Fry D202 Bedroom       Fry D202 HVAC      Fry D202 Living Room

                           Fry D202 Kitchen            Fry D202 Kitchen Closet                                


Update (June 2, 2007)

  • Demolition is underway.
  • Mechanical systems and fire prevent systems are being installed.
  • The first inspection is scheduled with the township for June 4th.
  • Contractors are working 5-6 days a week and are on schedule.
Update (May 21, 2007)
The contractors are clearing out all the furniture in Fry apartments and the demolition work will begin this week. Window replacement has been ongoing. Work in Fry D202 started this spring semester as a test apartment; the pictures show some of the work.

Pictures:
(Please click on any of the pictures below to see a larger image.)

Click here to see a larger version of the picture Click here to see a larger version of the picture    
Fry C Section
Fry A Section Closets
   
       
Click here to see a larger version of the picture Click here to see a larger version of the picture Click here to see a larger version of the picture Click here to see a larger version of the picture
New Windows
Fry Bathroom
Bedroom with New Closet
Hallway Piping
Click here to see a larger version of the picture Click here to see a larger version of the picture Click here to see a larger version of the picture  
Fry Cooling Tower
Fry D202
Fry D202 Closet
Click here to see a larger version of the picture Click here to see a larger version of the picture    
Fry Hallway
Kitchen Closets