Calvin and Janet High Center for Worship and Performing Arts
Artist Renderings of the Calvin and Janet High Center for Worship and Performing Arts
Work will begin on the water line replacement along College Ave from the South Entrance to the existing CFA (Climenhaga Fine Arts) Parking Lot. This work will involve excavation and the removal of the sidewalk from the CFA Parking Lot down the hill to the South Entrance. Employees and students are asked to use the sidewalk that runs between CFA and the Climenhaga Homestead. We expect that the sidewalk that runs from the CFA Parking Lot to the South Entrance will be closed for the duration of the construction of the High Center. Any questions should be directed to 691-6011, Facility Services.
Follow this link to see the pedestrian and construction access areas for the construction site. This map also shows the new one way traffic plan while construction is under way.
Calvin and Janet High Center for the Performing Arts Construction
May 24, 2012
Mixing cement Catwalk

CFAC office hallway Office of the Chair

Staircase Staircase 2

Connection to CFAC Digging carefully

Drainage work Drywall in an office

Elevator Frame work for entrance glass

Future home of the Class of 2012 gift Future home of the organ

Hot water Instrumental hall window

Instrumental hall Rectial hall entrance areas

Restroom Spot light location

Staircase area Window bulk head

Wire tray Sign install
May 22, 2012
The Messiah College sign arrives on campus
and is set in its place on the new High Center.
May 16, 2012
CFAC Lobby Windows are gone
No entrance to Poorman Poorman entrance is closed

Poorman before demo Off stage area

Poorman stage is gone Poorman demo 2

Poorman entrance to stage Coneection point
High Center to CFAC No window to the High Center

We are connected Paver demo

Entrance work Sidewalk work
May 7, 2012

Back of house area College Avenue

Detailed window work Drywall in the balcony

Front of bulding Getting ready for the Messiah College sign

Future site of the sound board Organ chamber

Pipe location for organ Progress on the balcony

Recording room (view one) Recording room (view two)

Sound booth in the hall Steel installation for catwalks

Stone work in hallway Stone work at the entrance near the
Department Chair office

Stone Windows in the Department Dean suite
Entrance area into the hall
April 19 , 2012

Work in the Hall Block Work

Connection point Duct work in Main Hall
Duct work wire trays piping Dump truck

Dump Truck 2 Entrance work
Finish work in the Hall Main Hall

Future stair location Insulation in the Main Hall

Inside block work Lower level side seating area prep

Lower level access Main Hall

Offices Ready for concrete

Recital Hall Side emergency exit

Staircase View from office
View of lower level
March 26 , 2012

Bathroom infrastructure Columns

Duct work in the main hall Duct work in the recital hall

Finishes in the main hall Future home of a staircase

Main hall finishes The president learning about the infrastructure

Stone work View from the choir loft

Wall work in the main hall Where buildings will soon connect
Window frames going in
March 9 , 2012

Brick work in progress Department Chair office

Choir and organ loft Creekside work

Dean's office Detailed wall finish

Employee lounge space Finishes in the main hall

HVAC system in the main hall Looking into instrumental rehearsal space
Main level finishes in the Hall Metal work on the hall

Metal work outside Recital hall back wall going up

Space for two piano studios View to upper level from the instrumental
rehearsal hall
February 16 , 2012

Soon the two buildings will be one Area looking at College Avenue

Bathroom Department Chair office

Choir loft and home of the pipe organ Choir loft storing duct work
The Dean's office In the hall looking at the stage
Inside looking out Instrumental rehearsal space

Lobby entrance Looking into CFAC where dressing rooms for Black Box will be
Looking out on the Yellow Breeches Lower level area where stairs will be located

Lower level hall Lower level temporary entrance to the building

Major mechanical duct work Where stairs will go from main level to lower level

Recital Hall Seating area of Recital Hall

Side view in the main hall of entrances Stage area of Recital Hall

Standing in the balcony looking at the choir loft View into College Avenue offices
January 5, 2012

Balcony seating in the main hall On stage in the hall

Creekside view of instrumental rehearsal hall Creekside view of the recital hall

Duct work Future home of the organ

Future instrumental storage room Lower level lobby

Lower level restroms Main hall stage view from seating area
Office hallway Office space at main entrance

South point entrance of campus Stairtower view of the Yellow Breeches
Standing in the instrumental rehearsal hall View of the upper level side seating in the hall
December 1 , 2011
The new building is really starting to come together now as you can see in the pictures below.


November 22 , 2011
Contractors continue to erect the steel. Decking is being placed and concrete flooring is being poured. Spray fire proofing is being applied to the structural steel. Back filling continues around the building foundation. The contractor continues to work towards closing the building in before cold winter weather approaches

October 7 , 2011
Some pictures of the progress......

September 23 , 2011
Over the next few weeks the contractor will continue to work on erecting the steel work. Decking will begin to be constructed in preparation for the concrete floors. The steel work will be focused on installation in the area of the new Auditorium. Backfilling of the foundations walls and masonry block walls will be coordinated between September and October. We will see contractors spraying fire proofing on the new steel beams.
Please monitor the project on the project live web cam that can be located at http://153.42.7.60/en/JViewer.html. Any questions regarding the construction of the High Center can be directed to Facility Services.

September 2 , 2011
The process of installing the structural steel at the High Center has begun. Contractors will be working over the next several weeks bolting and welding the structure together. As the steel goes up, the block work continues. Over the next few weeks there will be times that Creekside Drive will need to be temporarily closed so that 63' pieces of steel can be off- loaded from tractor trailer trucks. Please visit the live camera feed located at the link above for daily ongoing progress of this project.

July 8 , 2011
Foundation work continues as the contractor pours building footers along College Avenue and tie the new foundations into the existing Fine Arts building. Wall sections are currently under construction and concrete pillars are being poured.
June 22 , 2011
Foundation work continues on the High Center project. The work to build the concrete walls along College Avenue is currently in progress. Window cut outs are easily seen now on the foundation walls along College Avenue. The elevator shaft has been drilled and the foundation for the elevator is almost complete. Structural steel work will soon begin on the High Center as the building comes up from the ground.
May 9 , 2011
Work continues on the High Center foundation. Concrete casts are being placed along the foundation wall on Creekside Dr. Fondation footer work has progressed from Creekside and will begin along College Ave in the coming weeks. Shoring and soil nailing has been completed along the College Ave side of the building. This was done in preparation for other foundation and footer work. For a live view of the site please visit our live webcam by clicking on the following link: http://153.42.7.60/en/JViewer.html
April 21, 2011
Excavation work has began at the Calvin and Janet High Center for the Performing Arts. Contractors have mobilized and the foundation work is well under way. Over the next several weeks excavation for building foundations will continue. As we get closer to the summer months plans are moving forward for additional subcontractor mobilization. Construction trailers for the various trades will be arriving soon and will be placed in the parking lot of the Fine Arts Building where other construction trailers are currently located. For a live camera view of the construction area please visit our Facility Services website. To see live webcam video of the construction site click on the link http://153.42.7.60/en/JViewer.html
Phase 2b - Mechanical Building
site Logistics Plan - Phase 2B - Mechanical Building
January 2011
Construction is moving along. The fencing is up around the construction site. Creekside Drive is now one-way traffic. Please see the above Site Logistics Plan for traffic flow and pedestrian walkways.
November 2010
Waterproofing -

Door frames are set -

Concrete walls in place -

United Water is currently cutting the Creekside Drive macadam for new Water Meter Pit.

October 2010
The supports for the walls are being constructed.
September 2010
Footers are poured to support the new mechanical building.
August 24, 2010
Phase 2b is scheduled to begin in early September. This is for the site of the mechanical room for the Calvin and Janet High Center for Worship and Performing Arts. Preliminary work to remove trees and put up the construction fence has begun.
Work has been completed to bring new electrical service to the existing Fine Art Center building.
WorshipandPerformingArtsCenter_phase1