Calvin and Janet High Center for Worship and Performing Arts

 

Artist Renderings of the Calvin and Janet High Center for Worship and Performing Arts

Work will begin on the water line replacement along College Ave from the South Entrance to the existing CFA (Climenhaga Fine Arts) Parking Lot. This work will involve excavation and the removal of the sidewalk from the CFA Parking Lot down the hill to the South Entrance. Employees and students are asked to use the sidewalk that runs between CFA and the Climenhaga Homestead. We expect that the sidewalk that runs from the CFA Parking Lot to the South Entrance will be closed for the duration of the construction of the High Center. Any questions should be directed to 691-6011, Facility Services.

 

Site Logistics Plan

Follow this link to see the pedestrian and construction access areas for the construction site.  This map also shows the new one way traffic plan while construction is under way.

 

 

Calvin and Janet High Center for the Performing Arts Construction

 

May 24, 2012

 

     Mixing cement     Catwalk  

 

                         Mixing cement                                                       Catwalk

 

     CFAC office hallway     Office of the Dean

                    CFAC office hallway                                                Office of the Chair

 

     Staircase      Staircase 2

                             Staircase                                                         Staircase 2

 

     Connection to CFAC      Digging carefully

                   Connection to CFAC                                                  Digging carefully

 

     Drainage work      Drywall in an office

                      Drainage work                                                   Drywall in an office

 

     Elevator      Framework for entrance glass

                             Elevator                                              Frame work for entrance glass

 

     Future home of the Class of 2012 gift      Furure home of the organ

          Future home of the Class of 2012 gift                          Future home of the organ

 

     Hot water      Instrumental hall window

                              Hot water                                                Instrumental hall window

 

     Instrumental hall      Recital hall entrance areas

                      Instrumental hall                                          Rectial hall entrance areas

 

     Restroom      Spot light location

                           Restroom                                                       Spot light location

 

     Staircase area      Window bulk head

                         Staircase area                                                Window bulk head

 

     Wire tray      Sign install

                       Wire tray                                                               Sign install

 

May 22, 2012

 

The Messiah College sign arrives on campus

and is set in its place on the new High Center.

     Messiah College sign arrives on campus      Unloading the Messiah College sign

 

     Staging the Messiah College sign      Staging the Messiah College sign

 

     Preparing the mount for the sign      Guiding the placement of the Messiah College sign

 

     Setting the Messiah College sign      Securing the Messiah College sign

    

 

    

May 16, 2012

 

     Lobby of CFAC    Windows gone    

                        CFAC Lobby                                                 Windows are gone

 

     No entrance to Poorman    Poorman entrance is closed 

                    No entrance to Poorman                                 Poorman entrance is closed

 

    Poorman before demo       Off stage area

                  Poorman before demo                                                  Off stage area

 

     Poorman stage is gone      Poorman demo 2

                 Poorman stage is gone                                              Poorman demo 2

      

     

     Poorman entrance to stage     Connection point

              Poorman entrance to stage                                       Coneection point

            

     High Center to CFAC     No window to the High Center

                  High Center to CFAC                                     No window to the High Center       

 

         

    We are connected     Paver demo

                     We are connected                                                   Paver demo

        

    Entrance work     Sidewalk work

                     Entrance work                                                      Sidewalk work

        

 

    

 

May 7, 2012

 

     Back of house area     College Avenue

                     Back of house area                                                College Avenue

             

 

     Detailed window work     Drywall in the balcony

                  Detailed window work                                              Drywall in the balcony

 

     Front of the building     Gettting ready for the Messiah College sign

                          Front of bulding                              Getting ready for the Messiah College sign

 

     Future site of the sound board     Organ chamber

              Future site of the sound board                                        Organ chamber

 

     Pipe location for the organ     Progress on the balcony

                  Pipe location for organ                                      Progress on the balcony

 

     Recording room (view 1)     Recording room (view 2)

               Recording room (view one)                                Recording room (view two)

 

     Sound booth in the Hall     Steel installation for catwalks

                 Sound booth in the hall                                      Steel installation for catwalks

 

     Stone work in hallway     Stone work in the entrance near the Department Chair office

                  Stone work in hallway                                  Stone work at the entrance near the

                                                                                           Department Chair office

 

     Stone     Windows in the Department Dean suite

                              Stone                                           Windows in the Department Dean suite

 

 

                                     Entrance area into the hall    

    

                                                  Entrance area into the hall

 

                                               

April 19 , 2012

 

     Work in the Hall     Block work

                       Work in the Hall                                                    Block Work

 

     Connection point     Duct work in Main Hall

                       Connection point                                             Duct work in Main Hall

 

     Duct work wire trays piping     Dump truck 

               Duct work wire trays piping                                           Dump truck

 

     Dump truck 2     Entrance work

                         Dump Truck 2                                                       Entrance work

 

     Finish work in the Hall     Main Hall  

                  Finish work in the Hall                                                       Main Hall

 

     Future stair location     Insulation in the Main Hall

                     Future stair location                                         Insulation in the Main Hall

 

     Inside block work     Lower level side seating area prep

                        Inside block work                                   Lower level side seating area prep

 

     Lower level access     Main Hall

                       Lower level access                                                  Main Hall

 

     Offices     Ready for concrete

                               Offices                                                     Ready for concrete

 

     Recital Hall     Side emergency exit

                          Recital Hall                                                 Side emergency exit

 

     Staircase     View from office

                           Staircase                                                     View from office

 

                                   View of lower level    

                                                     View of lower level

    

 

March 26 , 2012

 

     Bathroom infrastructure      Columns

                 Bathroom infrastructure                                                  Columns

 

     Duct work in the main hall      Duct work in the recital hall

               Duct work in the main hall                                     Duct work in the recital hall

 

     Finishes in the main hall      Future home of a staircase

                Finishes in the main hall                                       Future home of a staircase

 

     Main hall finishes      President learning about the infrastructure

                     Main hall finishes                                The president learning about the infrastructure

 

     Stone work      View from the choir loft

                          Stone work                                                 View from the choir loft

 

     Wall work in the main hall      Where the two buildings will soon connect

                Wall work in the main hall                                Where buildings will soon connect

 

                                       Window frames gong in     

                                                    Window frames going in

 

 

March 9 , 2012

 

     Brick work in progress     Department Chair office

    

                 Brick work in progress                                        Department Chair office

 

     Choir and organ loft     Creekside work

                    Choir and organ loft                                             Creekside work

 

     Dean's Office     Detailed wall finish

                          Dean's office                                                 Detailed wall finish

 

     Employee lounge space     Finishes in the main hall

                     Employee lounge space                                  Finishes in the main hall

 

     HVAC system in the main hall     Looking in to instrumental rehearsal space

                HVAC system in the main hall                     Looking into instrumental rehearsal space

 

     Main level finishes in the hall     Metal work on hall 

              Main level finishes in the Hall                                     Metal work on the hall

 

     Metal work outside     Recital Hall back wall going up

                   Metal work outside                                       Recital hall back wall going up

 

     Space for two piano studios     View to upper level from instrument rehearsal hall

                Space for two piano studios                         View to upper level from the instrumental

                                                                                 rehearsal hall          

        

 

February 16 , 2012

 

     soon the two buildings will be one     area looking at College Avenue

            Soon the two buildings will be one                        Area looking at College Avenue

 

     bathroom     Department Chair's office

                           Bathroom                                                Department Chair office

 

     choir loft and home of the pipe organ     choir loft storing duct work

           Choir loft and home of the pipe organ                      Choir loft storing duct work

 

     Dean's office     in the hall looking at the stage

                         The Dean's office                                    In the hall looking at the stage

       

 

     inside looking out    instrumental rehearsal space

                       Inside looking out                                     Instrumental rehearsal space

 

     lobby entrance     looking into CFAC where dressing rooms for Black Box will go

                      Lobby entrance                                 Looking into CFAC where dressing rooms for                                                                                                      Black Box will be

 

     looking out on the Yellow Breeches     lower level area where stairs will be locatd 

          Looking out on the Yellow Breeches                Lower level area where stairs will be located    

 

     lower level hall     lower level temporary entrance to the building

                      Lower level hall                                Lower level temporary entrance to the building     

 

     major mechanical duct work    where stairs will go from main level to lower level

                Major mechanical duct work                          Where stairs will go from main level                                                                                                    to lower level

 

     recital hall     seating area of the recital hall

                           Recital Hall                                            Seating area of Recital Hall

 

     side view in main hall of entrances    stage area of recital hall

         Side view in the main hall of entrances                        Stage area of Recital Hall

 

     standing in the balcony looking at the choir loft     view into College Avenue offices

     Standing in the balcony looking at the choir loft         View into College Avenue offices

    

 

 

January 5, 2012

 

     Balcony seating in main hallway     On stage in the hall

           

              Balcony seating in the main hall                                On stage in the hall

 

     Creekside view of instrumental rehearsal hall     Creekside view of the recital hall

     Creekside view of instrumental rehearsal hall              Creekside view of the recital hall

 

     Duct work going on     Future home of the organ

                 

                               Duct work                                         Future home of the organ

 

     Future instrumental storage room     Lower level lobby

            Future instrumental storage room                                Lower level lobby

 

       Lower level restrooms     Main hall stage view seating area

                      Lower level restroms                                Main hall stage view from seating area

 

       Office hallway     Office space at main entrance

                         Office hallway                                           Office space at main entrance

 

      Southpoint entrance of campus      Stairtower viw of the Yellow Breeches

              South point entrance of campus                       Stairtower view of the Yellow Breeches

 

      Standing in the instrumental rehearsal hall     View of upper level side seating in the hall 

        Standing in the instrumental rehearsal hall         View of the upper level side seating in the hall

 

    

 

December 1 , 2011

 

The new building is really starting to come together now as you can see in the pictures below.

 

     Work in Progress     Closing in the Bulding

 

                                      A Future Dean's Office

 

 

November 22 , 2011

 

Contractors continue to erect the steel. Decking is being placed and concrete flooring is being poured. Spray fire proofing is being applied to the structural steel. Back filling continues around the building foundation. The contractor continues to work towards closing the building in before cold winter weather approaches

 

     erection of steel beams  fire proofing on steel

 

                      panoramic view

 

 

October 7 , 2011

 

Some pictures of the progress......

 

     steel beams in place   another view

 

                                        preparing the flooring  

 

September 23 , 2011

 

Over the next few weeks the contractor will continue to work on erecting the steel work. Decking will begin to be constructed in preparation for the concrete floors. The steel work will be focused on installation in the area of the new Auditorium. Backfilling of the foundations walls and masonry block walls will be coordinated between September and October. We will see contractors spraying fire proofing on the new steel beams.

 

Please monitor the project on the project live web cam that can be located at http://153.42.7.60/en/JViewer.html. Any questions regarding the construction of the High Center can be directed to Facility Services.

 

   High Center progress    High Center progress

 

September 2 , 2011

 

The process of installing the structural steel at the High Center has begun. Contractors will be working over the next several weeks bolting and welding the structure together.  As the steel goes up, the block work continues.  Over the next few weeks there will be times that Creekside Drive will need to be temporarily closed so that 63' pieces of steel can be off- loaded from tractor trailer trucks.  Please visit the live camera feed located at the link above for daily ongoing progress of this project.

 

   Steel beams put in place     Progress on beams continues

 

July 8 , 2011

 

Foundation work continues as the contractor pours building footers along College Avenue and tie the new foundations into the existing Fine Arts building.  Wall sections are currently under construction and concrete pillars are being poured.

 

    Foundation walls   Foundation Footers

 

June 22 , 2011

 

Foundation work continues on the High Center project.  The work to build the concrete walls along College Avenue is currently in progress.  Window cut outs are easily seen now on the foundation walls along College Avenue.  The elevator shaft has been drilled and the foundation for the elevator is almost complete.  Structural steel work will soon begin on the High Center as the building comes up from the ground.

 

     Foundation walls going up                 Elevator shaft

 

May 9 , 2011

 

Work continues on the High Center foundation. Concrete casts are being placed along the foundation wall on Creekside Dr. Fondation footer work has progressed from Creekside and will begin along College Ave in the coming weeks. Shoring and soil nailing has been completed along the College Ave side of the building. This was done in preparation for other foundation and footer work. For a live view of the site please visit our live webcam by clicking on the following link: http://153.42.7.60/en/JViewer.html

 

        Foundation walls going up        Foundation Walls

 

April 21, 2011

 

Excavation work has began at the Calvin and Janet High Center for the Performing Arts. Contractors have mobilized and the foundation work is well under way. Over the next several weeks excavation for building foundations will continue. As we get closer to the summer months plans are moving forward for additional subcontractor mobilization. Construction trailers for the various trades will be arriving soon and will be placed in the parking lot of the Fine Arts Building where other construction trailers are currently located. For a live camera view of the construction area please visit our Facility Services website.  To see live webcam video of the construction site click on the link http://153.42.7.60/en/JViewer.html

 

                 Excavation has begun                       Excavation

 

Phase 2b - Mechanical Building

site Logistics Plan - Phase 2B - Mechanical Building

 

January 2011

 

Construction is moving along.  The fencing is up around the construction site.  Creekside Drive is now one-way traffic.  Please see the above Site Logistics Plan for traffic flow and pedestrian walkways.

 

     Creekside View     Old Main View  

 

     Another Old Main View     South Entrance View

           

 

 

November 2010

 

Waterproofing -

 

 water proofing     polystyrene rigid insulation

 

Door frames are set -

 

Door Frame set in

 

Concrete walls in place -

 

Concrete Walls       Concrete Walls

 

United Water is currently cutting the Creekside Drive macadam for new Water Meter Pit.

 

United Water preparing for Water Meter Pit       United Water preparing for Water Meter Pit

 

October 2010

 

The supports for the walls are being constructed.

 

wall supports go up   wall supports are constructed

 

September 2010

 

Footers are poured to support the new mechanical building.

 

footers for mechanical room   footers poured for mechanical building  

 

 

August 24, 2010

Phase 2b is scheduled to begin in early September.  This is for the site of the mechanical room for the Calvin and Janet High Center for Worship and Performing Arts.  Preliminary work to remove trees and put up the construction fence has begun.

 

Work has been completed to bring new electrical service to the existing Fine Art Center building.

Area for Mechanical Building   

 

Looking from the Covered Bridge

 

WorshipandPerformingArtsCenter_phase1