Calvin and Janet High Center for Worship and Performing Arts
High Center Soft Opening
You are invited to join us for the opening of the Calvin and Janet High Center for Worship and Performing Arts on Monday, Jan. 14, 2013. Our campus community has been eagerly anticipating the completion of this wonderful new facility for nearly two years. To celebrate, please come at 7:40 a.m. to the patio area of the Climenhaga Building and the High Center. At that time, Richard Roberson, dean of the school of the arts, will open the front doors of the building and invite employees and students to enter. Enjoy a few minutes informally exploring the building before you start your day.
While Parmer Hall (the main auditorium) and the High Foundation Recital Hall will not be open until the end of January, we are already planning our first public events in those venues. The first recital is scheduled for Jan. 27, and the first concert in Parmer Hall is scheduled for Feb. 17. The College will host a special all-employee chapel to commemorate the opening of the High Center in Parmer Hall on Feb.27, at 3:00 p.m. The announcement of the inaugural public event season for the High Center during the 2013-2014 academic year will be announced later this spring. Thank you to everyone in the Messiah College community who has played a part in planning, fundraising, developing and readying the High Center for use by our campus and the broader region, I hope you can join us for these upcoming events.
Artist Renderings of the Calvin and Janet High Center for Worship and Performing Arts
Work will begin on the water line replacement along College Ave from the South Entrance to the existing CFA (Climenhaga Fine Arts) Parking Lot. This work will involve excavation and the removal of the sidewalk from the CFA Parking Lot down the hill to the South Entrance. Employees and students are asked to use the sidewalk that runs between CFA and the Climenhaga Homestead. We expect that the sidewalk that runs from the CFA Parking Lot to the South Entrance will be closed for the duration of the construction of the High Center. Any questions should be directed to 691-6011, Facility Services.
Follow this link to see the pedestrian and construction access areas for the construction site. This map also shows the new one way traffic plan while construction is under way.
Calvin and Janet High Center for the Performing Arts
Construction
April 4, 2013
Completed photos -

Classroom Seating Restroom

Stairs Blackbox Seating

Rehearsal Space Music Library

Piano Lab Parmer Hall Seating
December 18, 2012

Art Hallway Bathroom fixtures

Spotlight Screen will fit between here

Tile flooring almost complete Signage for Black Box

Black Box floor Black Box lighting

Stairs to the Black Box Step 3 in Black Box flooring

Catwalk view Clearing the stage

Counter at stage booth Jon Berrt and his toys

Lighting in the sound booth Moveable panels from the catwalk

Elevator shaft Painting in the hall
Parmer Hall sign Parmer Hall

Recital hall name High Foundation

Recital hall paneling Recital hall railing

Start of stage flooring Stage flooring 2

Start of stage flooring Step 2 of Stage flooring

Chamber Music flooring Stain option for Parmer Hall

Curtains Flooring sub floor

Flooring Recording Studio

Restroom sign Signage

Rear entrance signage View from the upper level

Furniture delivery Melhart

Furniture for the Dean's office Furniture in the Dean's suite

Dean's desk and guest chairs Dean's desk

Dean's guest seats Dean's table

Chair's suite Department Chair's desk and chair

Faculty desk Mirror for Teaching Studio

Nesting tables Office bookcase

Educator chair We have an address!
December 7, 2012
Organ blowers Back of house blackbox

Blackbox panels Blackbox

Carpet in seminar room Carpet in tech lab

Office of the Chair Choir loft

Classroom ready for AV Connection almost done

Dressing room Faculty hallway

Flooring Getting ready for flooring

Instrumental rehearsal Instrument repair space

Organ parts Organ pieces

Paving Railing

Rear stairs Recital Hall lights

Recital Hall stage Recital Hall

Side seating Side seating 2

Stair work View to Art Gallery

Instrumental rehearsal final flooring
November 9, 2012

Art install Back of house restroom

Blackbox control area Class of 2012 senior gift

College Avenue landscape College Avenue

Doors being installed Drywall area in hall

Employee lounge Flooring in practice room

Keyboard lab raised floor Keyboard lab raised floor - 2

Keyboard lab Landscape work

Landscaping Movable sound clouds

Organ screens Outside work

Paneling Parmer Hall work

Parmer Hall Paver area

Ready for pavers Prep for tile at entrance

Ready for the organ Recital hall sound clouds

Rectial hall Recording studio

Restroom South Gate view of High Center

South Gate view Stair tower

Tile install Tile on lower level

Tile Trash and recycling area

High Center
November 2 , 2012

Choral Contractors everywhere

Drywall in recital hall Entrance paneling

Entrance work Lights
Lobby work Lower level tile prep

Outside Blackbox Paneling lower level

Paneling Panels

Practice room Rear entrance

Recital Hall
October 24, 2012
A hint of art Beautiful wood

Blackbox Catwalk view of the hall

Ceiling in rehearsal space Columns in the hall

Entrance work for doors Entrance

ITS Wiring Lighting

Lights in the lobby Lobby work

Lower level ready for stairs Main wall

Major staircase Mechanical systems for the building

Mechanicals on roof Music Library

Office on lower level Paneling in the hall

Parking area Paving round 1

Prep for tile Prepping wood

Rain garden class of 2012 gift Ready for paneling

Rear entrance Recital hall
Restroom Restroom 2

Restroom 3 Restroom floor tile

Retention Roof panels

Roof view of entrance Roof view of stairs

Sidewalk prep South gate work

Staircase Stairwell

Steel for floating stairs Upper rain garden

Upper seating area View of parking from the roof

View of the Climenhaga patio from the roof View to upper level
October 9, 2012

Accoustic panel in office Address wireless issues

Blackbox ceiling Blackbox

Ceiling grid - intstrumental rehearsal area Ceiling grid in lobby

Ceiling work Choir loft

Dressing room for the dance studio Hall work

Hallway work ITS room with miles of wire

Lower lobby work Main hall sound area

Main hall work Mixing are ain the hall

Parking lot work Rear entrance

Seating area work Sound booth ready for drywall

Start of retention area in parking lot Tile in restroom

Wiretray
September 21, 2012

Black Box Choral Paint Work

Classroom Dean's Suite
Deans on stage Ensemble space

Entrance Future water garden (Sr. class gift)

Hall work Instrumental room and paint

Main Hall work Main Hall

Office paint Parking lot work begins

Parking lot work begins Rear entrance

Rear entrance Recording studio

Retention area at South Gate South Gate area of High Center

Seating area of Hall Stage area

Steel for stairs Retention area

Retention area 2 Retention area 3

Retention area 4 Teaching studio flooring

Tile installed in the bathroom Black Box entry
August 1 , 2012

Architects on Stage Art Wall

Balcony Seating Blackbox 2nd Floor Seating Area

Blackbox Catwalk View of Organ

Catwalk View of Seating Catwalk View of Sound Clouds

Catwalk CFAC Music Hallway

Closing Up Curved Wall

Entrance Exit Ramp

Floor Lighting Instrumental Rehearsal

Landing to Second Floor for Blackbox Lobby View

New Benches New Connection Point

New Door to Poorman Blackbox New Doors

New Stairs to Lower CFAC New Storage Units

No More Trucks in the Hall Office of the Dean

Old Door to Poorman is Gone On Stage Looking Out

Organ Chambers Pipe for the Organ

Power to the Sound Board Practice Room Row

Prepping the Seating Area Ready for Aisle Lights

Ready for Stairs Restroom

Roof Inspection Roof Unit

Roof View of Building Sound Clouds
Stage in Recital Hall Stage

Stair Area Stairs to the Second Level of Poorman

Steel for the Organ Area View from the Roof

Waiting for Glass Waiting for Stairs
Stage in Main Hall
July 26, 2012

Back Hallway Bible Verse Wall

Deck for Stage - Lower Area Deck for Stage

Drywall in the Chair's Office Entrance View from the Dean's Office

Faculty Hallway Future Connection to CFAC

Lobby Area New Pavers

Patio Area Side Exit

Stage Work Stud Work in the Dean's Suite

View from the Chair's Office View from the Dean's Office
July 23, 2012
Organ Rebuild
The swell division windchests set up in the Releathered pouchboards - these set under
shop with pipes being fitted pipes and collapse to allow wind to play the
pipes
Parts being made The old console shell with the new layout in
paper overlays
Redrilling of rackboards to accommodate pipes
being moved from one division to another
July 13, 2012
Catwalk look into organ area Catwalk view of hall
Catwalk view of the balcony Catwalk view
Clouds to be installed Installation of first cloud

Cloud installed Cloud

Entrance from Starry side Instrumental rehearsal

Mechanical wench for clouds Winch work

Roof view Roof
July 12, 2012

Blackbox Blackbox Mezzane
Dressing Room for Blackbox Ceiling Work

Connection between CFAC and High Center Duct Work in the Hall

Organ Area Entrance Area to the Building

Lobby Space Drywall New Hall
Old Entrance to Poorman Outside Wall of the New Recital Hall

Outside Paver Work New Pavers
June 13, 2012

Instrumental Hall Mezz Seating

Poorman Blackbox Practice Areas

Recital Hall Rehearsal Space

Roof Soon to Come Off of Poorman Seating Area

Stairwell Area
May 24, 2012
Mixing cement Catwalk

CFAC office hallway Office of the Chair

Staircase Staircase 2

Connection to CFAC Digging carefully

Drainage work Drywall in an office

Elevator Frame work for entrance glass

Future home of the Class of 2012 gift Future home of the organ

Hot water Instrumental hall window

Instrumental hall Rectial hall entrance areas

Restroom Spot light location

Staircase area Window bulk head

Wire tray Sign install
May 22, 2012
The Messiah College sign arrives on campus
and is set in its place on the new High Center.
May 16, 2012
CFAC Lobby Windows are gone
No entrance to Poorman Poorman entrance is closed

Poorman before demo Off stage area

Poorman stage is gone Poorman demo 2

Poorman entrance to stage Coneection point
High Center to CFAC No window to the High Center

We are connected Paver demo

Entrance work Sidewalk work
May 7, 2012

Back of house area College Avenue

Detailed window work Drywall in the balcony

Front of bulding Getting ready for the Messiah College sign

Future site of the sound board Organ chamber

Pipe location for organ Progress on the balcony

Recording room (view one) Recording room (view two)

Sound booth in the hall Steel installation for catwalks

Stone work in hallway Stone work at the entrance near the
Department Chair office

Stone Windows in the Department Dean suite
Entrance area into the hall
April 19 , 2012

Work in the Hall Block Work

Connection point Duct work in Main Hall
Duct work wire trays piping Dump truck

Dump Truck 2 Entrance work
Finish work in the Hall Main Hall

Future stair location Insulation in the Main Hall

Inside block work Lower level side seating area prep

Lower level access Main Hall

Offices Ready for concrete

Recital Hall Side emergency exit

Staircase View from office
View of lower level
March 26 , 2012

Bathroom infrastructure Columns

Duct work in the main hall Duct work in the recital hall

Finishes in the main hall Future home of a staircase

Main hall finishes The president learning about the infrastructure

Stone work View from the choir loft

Wall work in the main hall Where buildings will soon connect
Window frames going in
March 9 , 2012

Brick work in progress Department Chair office

Choir and organ loft Creekside work

Dean's office Detailed wall finish

Employee lounge space Finishes in the main hall

HVAC system in the main hall Looking into instrumental rehearsal space
Main level finishes in the Hall Metal work on the hall

Metal work outside Recital hall back wall going up

Space for two piano studios View to upper level from the instrumental
rehearsal hall
February 16 , 2012

Soon the two buildings will be one Area looking at College Avenue

Bathroom Department Chair office

Choir loft and home of the pipe organ Choir loft storing duct work
The Dean's office In the hall looking at the stage
Inside looking out Instrumental rehearsal space

Lobby entrance Looking into CFAC where dressing rooms for Black Box will be
Looking out on the Yellow Breeches Lower level area where stairs will be located

Lower level hall Lower level temporary entrance to the building

Major mechanical duct work Where stairs will go from main level to lower level

Recital Hall Seating area of Recital Hall

Side view in the main hall of entrances Stage area of Recital Hall

Standing in the balcony looking at the choir loft View into College Avenue offices
January 5, 2012

Balcony seating in the main hall On stage in the hall

Creekside view of instrumental rehearsal hall Creekside view of the recital hall

Duct work Future home of the organ

Future instrumental storage room Lower level lobby

Lower level restroms Main hall stage view from seating area
Office hallway Office space at main entrance

South point entrance of campus Stairtower view of the Yellow Breeches
Standing in the instrumental rehearsal hall View of the upper level side seating in the hall
December 1 , 2011
The new building is really starting to come together now as you can see in the pictures below.


November 22 , 2011
Contractors continue to erect the steel. Decking is being placed and concrete flooring is being poured. Spray fire proofing is being applied to the structural steel. Back filling continues around the building foundation. The contractor continues to work towards closing the building in before cold winter weather approaches

October 7 , 2011
Some pictures of the progress......

September 23 , 2011
Over the next few weeks the contractor will continue to work on erecting the steel work. Decking will begin to be constructed in preparation for the concrete floors. The steel work will be focused on installation in the area of the new Auditorium. Backfilling of the foundations walls and masonry block walls will be coordinated between September and October. We will see contractors spraying fire proofing on the new steel beams.
Please monitor the project on the project live web cam that can be located at http://153.42.7.60/en/JViewer.html. Any questions regarding the construction of the High Center can be directed to Facility Services.

September 2 , 2011
The process of installing the structural steel at the High Center has begun. Contractors will be working over the next several weeks bolting and welding the structure together. As the steel goes up, the block work continues. Over the next few weeks there will be times that Creekside Drive will need to be temporarily closed so that 63' pieces of steel can be off- loaded from tractor trailer trucks. Please visit the live camera feed located at the link above for daily ongoing progress of this project.

July 8 , 2011
Foundation work continues as the contractor pours building footers along College Avenue and tie the new foundations into the existing Fine Arts building. Wall sections are currently under construction and concrete pillars are being poured.
June 22 , 2011
Foundation work continues on the High Center project. The work to build the concrete walls along College Avenue is currently in progress. Window cut outs are easily seen now on the foundation walls along College Avenue. The elevator shaft has been drilled and the foundation for the elevator is almost complete. Structural steel work will soon begin on the High Center as the building comes up from the ground.
May 9 , 2011
Work continues on the High Center foundation. Concrete casts are being placed along the foundation wall on Creekside Dr. Fondation footer work has progressed from Creekside and will begin along College Ave in the coming weeks. Shoring and soil nailing has been completed along the College Ave side of the building. This was done in preparation for other foundation and footer work. For a live view of the site please visit our live webcam by clicking on the following link: http://153.42.7.60/en/JViewer.html
April 21, 2011
Excavation work has began at the Calvin and Janet High Center for the Performing Arts. Contractors have mobilized and the foundation work is well under way. Over the next several weeks excavation for building foundations will continue. As we get closer to the summer months plans are moving forward for additional subcontractor mobilization. Construction trailers for the various trades will be arriving soon and will be placed in the parking lot of the Fine Arts Building where other construction trailers are currently located. For a live camera view of the construction area please visit our Facility Services website. To see live webcam video of the construction site click on the link http://153.42.7.60/en/JViewer.html
Phase 2b - Mechanical Building
site Logistics Plan - Phase 2B - Mechanical Building
January 2011
Construction is moving along. The fencing is up around the construction site. Creekside Drive is now one-way traffic. Please see the above Site Logistics Plan for traffic flow and pedestrian walkways.
November 2010
Waterproofing -

Door frames are set -

Concrete walls in place -

United Water is currently cutting the Creekside Drive macadam for new Water Meter Pit.

October 2010
The supports for the walls are being constructed.
September 2010
Footers are poured to support the new mechanical building.
August 24, 2010
Phase 2b is scheduled to begin in early September. This is for the site of the mechanical room for the Calvin and Janet High Center for Worship and Performing Arts. Preliminary work to remove trees and put up the construction fence has begun.
Work has been completed to bring new electrical service to the existing Fine Art Center building.