The college has been in negotiations with UGI and UGI Performance Solutions to bring natural gas to campus and build a Combined Heat and Power Plant (CHPP). Borrowing for this project will not exceed $7.5 million. Natural gas connections are expected to be ready for on campus use by spring 2016. Significant annual savings in utilities expenditures in excess of $800,000 will be achievable immediately following construction.


August 21st - Work has begun



August 25, 2015 -




August 26, 2015 -

September 1, 2015 -

September 8, 2015 -

September 21, 2015




September 22, 2015
Installing pipe for natural gas
September 25, 2015 -



Gas line approach main -

September 30, 2015 -

October 1, 2015 -
Gas approach main



October 13, 2015 -



October 15, 2015 -
Main Approach


October 19, 2015
CHP

Approach Main



October 29, 2015 -




October 29, 2015 -




November 2, 2015
Approach Main


November 5, 2015 -
November 24, 215 -




December 14, 2015 -




December 22, 2015 -







January 5, 2016 -









January 7, 2016
Gas Lines




January 19, 2016 -






February 2, 2016 -
February 4, 2016 -




March 1, 2016 -
March 15, 2016
March 29, 2016 -
The CHP is complete and generating electricity for the Eisenhower Campus Center and the Sollenberger Sports Center.